Northeast 130th Avenue

Update - Sept. 2024

Work in the roadway will be completed this week. Electrical work will be done at a later time as materials have a long delivery time. Additional work in the roadway may be needed at that time.

NE 130th Ave - Overview

Project Details

Safety improvements are coming to Northeast 130th Avenue between Northeast 76th Street and Padden Parkway.  Public Works will install improvements including a marked crosswalk with lighting and a flashing beacon at the intersection of Northeast 130th Avenue and the Padden Parkway multi-use trail; upgrading the crosswalk in the school zone at Heritage High School and installing new school zone flashers; rebuilding sidewalk curb ramps to meet Americans with Disabilities Act (ADA) requirements; installing ADA-compliant crosswalk buttons; upgrading bike lane markings; and installing pedestrian, school zone and transit signage.

The project includes design, engineering, surveying, environmental documentation/permitting, storm drainage, right of way acquisition, and construction. All documents, engineering, plans and specifications will be completed in accordance with all applicable federal, state and county standards.

Funding

The total budget identified for the project is $525,000. The county received a grant from the Washington State Transportation Improvement Board (“TIB”) in the amount of $500,000 for project design and construction.

Schedule 

Design:             spring 2023 – fall 2024
Construction:    This project is expected to go to construction in the summer 2024.

Mailers

June 2024 Postcard (PDF)
April 2023 Heads up (PDF)

More information:

Paul Morin, Project Manager
Clark County Public Works
564.397.4394
paul.morin@clark.wa.gov