Construction Traffic Delays

Week of May 16, 2022 

Roadway Conditions

Clark County  564.397.6118

Northeast 10th Avenue (Northeast 149th Street to Northeast 154th Street)

A county project will reconstruct the roadway to include two travel lanes, center left-turn lane, bike lanes, sidewalks, stormwater treatment facilities, a culvert crossing and a traffic signal at the intersection with NE 149th St. Associated utility work will also be completed. The project is scheduled to be completed in June 2022.

The intersection of Northeast 149th Street and Northeast 10th Avenue will be closed to all traffic for up to 30 days, beginning the morning of Apr. 25, 2022. A detour will be in place to take pedestrian and vehicular traffic east/west on Northeast 146th Street and north/south on Northeast 4th Avenue. To avoid the detour, drivers can travel north/south on Northwest 21st Avenue between Northwest 139th Street and Northwest 149th Street. Drivers are urged to use this alternative route, rather than the detour, to minimize traffic impacts to the adjacent neighborhood.

Northeast 10th Avenue will remain closed to through-traffic between the intersections of Northeast 149th Street and Northeast 154th Street until June 2022. Adjacent driveways on Northeast 10th Avenue are accessible from the north. The two intersections are open to traffic although subject to temporary, flagger-controlled delays. The Northeast 154th Street intersection will be remain open to traffic but may see some traffic control if necessary. Drivers are urged to use caution for flaggers and workers on the roadway shoulders.

HMAs 
Beginning Monday, May 16, crews will begin to seal cracks in the roads and pave some small areas that have sunk or deteriorated. There may be some traffic delays, as travel lanes may be reduced or shifted at times or controlled by pilot car. Flaggers will help guide drivers around the work areas.
Crews will be at the following locations:

  • NE Rosewood Avenue
  • SE Crown Road
  • NE 50th Avenue
  • NE 72nd Street
  • NE 76th Street
  • NE 76th Street & NE 117th Ave.
  • NE Ward Road
  • NE 217th Avenue​​​​​​

Work will be performed at various county locations between the hours of 7 am and 7 pm, Monday through Friday. Work is scheduled to be completed by the beginning of September 2022. The completion of this work is weather dependent.

Northeast 99th St

A private contractor will be working to install utilities for a private development on 99th Street between NE 25th Ave and NE 33rd Ave. Drivers should expect traffic revisions within the area between the hours 9 am and 3 pm. Work is scheduled to be complete by the end of June 2022.

Northeast 78th St and Northeast Saint Johns Rd

A private contractor will be working to install utilities for a private development on 78th Street between St. Johns and NE 39th Ct and also on St. Johns between NE 78th St to NE 43rd Ave.  Drivers should expect traffic revisions within the area between the hours 9 am and 3 pm. Work is scheduled to be complete by the end of June 2022.

NE 117th St (NE Hazel Dell Ave to NE 3rd Ave)

A private contractor will be working to install utilities for a private development that will be built between NE 117th St and NE Bassel Rd.  Drivers should expect traffic revisions within the area. Work is scheduled to be complete by the end of June 2022.

NE 50th Ave at NE 159th St to NE 179th St

A private contractor will be working to install utilities for a private development.  Drivers should expect traffic revisions within the area. Work is scheduled to be complete by the end of June 2022.

NE 25th St.  at NE 82nd St to NE 88th St.

A private contractor will be working to install utilities for a private development.  Drivers should expect traffic revisions within the area. Work is scheduled to be complete by the end of June 2022.

NE 179th St. at NE 11th Ave to NE 10th Ave

A private contractor will be working to install utilities and build our frontage for a private development.  Drivers should expect traffic revisions within the area. Work is scheduled to be complete by the end of June 2022.

NE 179th St at NE 15th Ave to NE 50th Ave

A private contractor will be working to install utilities and build our frontage for a private development.  Drivers should expect traffic revisions within the area. Work is scheduled to be complete by the end of June 2022.

NE 88th St. at NE 72nd Avenue  to NE 79th Ct

A private contractor will be working to install utilities and build our frontage for a private development.  Drivers should expect traffic revisions within the area. Work is scheduled to be complete by the end of June 2022.

NE 72nd Ave at NE 123rd St. to NE 119th St.

A private contractor will be working to install utilities and build our frontage for a private development.  Drivers should expect traffic revisions within the area. Work is scheduled to be complete by the end of June 2022.

NE 99th Street (NE 94th Avenue to SR503)
Beginning March 1, 2022, a county project will construct a new section of roadway over the north section of the Leichner Landfill as well as three roundabouts (NE 94th Avenue, NE 107th Avenue, NE 110th/112th Avenue), building walls, widening the existing roadway and adding sidewalks / bike facilities.  The project is scheduled to complete in the fall 2023.

Volunteer Events
Saturday, 05/14

  • Crossroads Church at Orchards Community Park
  • CVAB - Adopt -A- Road 

Monday, 05/16

  • Lewisville Walkers AAP cleanup

Tuesday, 05/17

  • Laseronics Adopt- A- Road 

Wednesday, 05/18

  • Church of Jesus Christ of Latter-day Saints - Adopt-A-Road

 


City of Vancouver 360.487.7750

Roadway Corridor Improvement Project: Utility Construction and Resurfacing
Construction on Phase II of the Broadway Corridor Improvement Project, from 6th to 13th Street, began February 14, 2022. Construction conditions, supplies and weather permitting, the project is currently expected to be substantially completed by summer 2022. This is part of a major upgrade of water and sewer infrastructure followed by repaving of Broadway Street. Phase II from 13th Street to McLoughlin Boulevard was completed in 2021. www.cityofvancouver.us/Broadway

Improvement Project: Land Bridge Paving and Overlook Renovation Project
The City of Vancouver has begun construction on a project to repair and renovate the popular Confluence Land Bridge, which arcs over State Route 14 east of Interstate 5. During this project, the city's contractor will remove failing decomposed granite surface on the Land Bridge, replacing it with architectural pavers, and renovate the People Overlook, also known as the Kanaka Village Overlook. The project is currently estimated to start in mid-October. Project completion is anticipated for early March 2022, weather and construction conditions permitting. 

SE 1st Street Improvement Project: SE 1st Street, 164th Avenue to 177th Avenue
Construction on the first segment of the SE 1st Street Improvement Project, 164th Avenue to 177th Avenue, started in early December 2021. This long-awaited transportation improvement project will provide a complete urban street system with sidewalks, bike facilities, stormwater enhancements, street lights and sound walls where designated. Project completion, including street paving, is currently anticipated about fall 2022. www.cityofvancouver.us/FirstStreet

Private Development Projects Citywide
A variety of private development projects may be occurring throughout the City of Vancouver. For information about these projects, please visit: www.cityofvancouver.us/projects.


Washington State Department of Transportation 360.905.2060

PLEASE NOTE: Daytime traffic impacts typically take place between 6 a.m. and 6 p.m., and nighttime impacts are between 6 p.m. and 6 a.m. Times may vary based on weather and other (construction-related) variables

I-5 – northbound between 17.2 and 19.0 – on the Lewis River Bridge
Freight travelers who use northbound Interstate 5 will temporarily shift to use the center lane along the northbound span of the Lewis River Bridge about two miles south of Woodland. Shifting large truck traffic to use the center lane of northbound I-5 helps prevent further damage to the bridge deck and extends the usable life of temporary repairs until more permanent repairs can be scheduled when warmer weather returns.