Construction Traffic Delays

Week of May 26, 2025

 

Clark County  564.397.6118

This webpage shows county projects on county roads that could have an impact on the traveling public. A variety of private development projects may be occurring throughout the county that might not be listed. For more information on proposed development projects, visit clark.wa.gov/community-development/proposed-developments. For more information on the process of approving proposed development projects visit, clark.wa.gov/community-development.


Non-construction closures

Hockinson Fun Days Parade – June 1st

There will be numerous road closures along Northeast 182nd Street, Northeast 159th Street, Northeast 179th Avenue, Northeast 170th Avenue, and Northeast 164th Street, starting at 11 a.m. Roads will be reopened after the parade ends. Click here to view the parade route. Click here to view the road closures.


Construction Closures and Delays

Traffic Signal Upgrades

This spring, Clark County will upgrade several traffic signals throughout the county. 

This work includes constructing or upgrading traffic and pedestrian signals at:

  • Northeast 27th Avenue at Northeast 134th Street
  • Northeast 7th Avenue at Northeast Fraser Road
  • Northeast 5th Avenue at Northeast 78th Street
  • Northeast Hazel Dell Avenue – from Northeast 78th Street to Northeast 82nd Street

Construction is expected to begin in mid-April. Construction activities will occur between 7 a.m. and 5 p.m. on weekdays. For the safety of workers and the public, traffic lanes and/or sidewalks may be temporarily closed near worksites. Travels will be directed around closed lanes and sidewalks.


CPUD B687 UG Cable Repl NE 27th Ave & NE 153rd St

Starting March 17, Clark Public Utilities will conduct work within the Four Creeks Neighborhood, Mt Vista area.  The work is estimated to last 3 months. The work will consist of replacing/upgrading existing power infrastructure within the Four Creeks Neighborhood.  Restoration should take place as they move throughout the neighborhood.  Traffic impacts should be minimal.  Click here to view the traffic control plans. Click here to view the construction area. Click here to view the project area. Click here to view the letters mailed to residents by Clark Public Utilities. 


Northeast 179th Street

Starting Tuesday, May 27, a single lane will be closed on Northeast 179th Street between Northeast 29th Avenue and Northeast 50th Avenue for a water tie. The lane should reopen on Wednesday, May 28. However, there will be steel sheets from Northeast 29th Avenue and Northeast 50th Avenue until Monday, June 2nd.


Northeast 119th Street and Northeast 152nd Avenue

The roadway is open to traffic. There is still work to be completed on-site. Traffic control will be present to direct travelers during any lane closures. The traveling public can expect delays due to these lane closures and construction.


Northeast Sunset Falls Road Pavement Preservation

Construction has been delayed until summer 2025 due to challenges in obtaining materials and the onset of cold and wet weather. 


Harmony Sports Complex

Construction at Harmony Sports Complex has begun. The contractor is continuing the installation of infiltration trenches and other stormwater structures.


Curtin Creek Community Park

Construction at Curtin Creek Community Park has begun. The park is anticipated to be open by spring 2026.


2025 Preservation ADA Improvements

Construction for this project has begun.  Impacts will include short delays, construction zones, and rerouting of pedestrians.


2024 ADA Ramp Improvement project


Northwest 78th Street

Continue to expect temporary lane closures on Northwest 78th Street as the project enters its final stages.  Lane closures will be marked with traffic cones and flaggers, who will direct traffic and pedestrians. Travelers along Northwest 78th Street may experience delays of up to 20 minutes.


Northeast 99th Street

On Northeast 99th Street, the road work is physically complete and open. Intermittent work on plant establishment will continue but traffic control is not expected to be employed.


Railroad Roadbed Rehabilitation Project

Construction began this week on the Railroad Roadbed Rehabilitation. This project is a rehab of the county-owned railroad track near Moulton Falls. The contractor plans on installing new railroad ties near Moulton Falls.  This project is scheduled to be completed before June 13, 2025.


NW 11th Ave between NW 149th St and NW 164th St

A contractor will be doing utility work and paving for a new development between now and mid-September. There will be a single lane closure with flaggers controlling traffic.


A contractor working at NW 99th Street at NW 9th Ave

Fink Construction is working for Clark Public Utilities Water to extend larger water pipes to the west.  They are digging a trench along NW 99th Street.  At a later time, they will dig into the side streets to make additional connections.  

With this activity, the vehicle detectors were dug up before schedule.  Our staff is working to provide alternate signal timing that accounts for variable traffic volumes and the high pedestrian traffic at the signal adjacent to the high school.

County engineers will monitor the intersection's performance through the first day of school and make any adjustments needed.  


Northshore Waterline - City of Camas

Northeast 28th Street and Northeast 232nd Avenue, Installing Mainline Water Main

Contact: Wisam Jawadi 1-360-335-5712 

Interstates, highways

Washington State Department of Transportation
360.905.2060


Private Development Projects Citywide
A variety of private development projects may be occurring throughout the City of Vancouver. For information about these projects, please visit: www.cityofvancouver.us/projects.