Week of Sept. 25, 2023
Clark County 564.397.6118
The contractor began work this week completing pavement repairs throughout the county in preparation for the chips seals that Clark County plant to place later this summer. Beginning Tuesday, June 20th , crews will being completing various repairs and mainline paving throughout the project limits. There may be some traffic delays, as travel lanes may be reduced or shifted at times or controlled by pilot car. Flaggers will help guide drivers around the work areas.
Crews will be at the following locations:
- NE 116th Avenue
- NE 65th Street
- NE 199th Avenue
- NE Vernon Road
- NE St. Johns Road
- NE Cramer Road
- NE 182nd Avenue
- NW Columbia Street
Work will be performed at various county locations typically between the hours of 8 am and 8 pm, Monday through Friday. Work is scheduled to be completed by the middle of August 2023. The completion of this work is weather dependent.
Northeast HWY 99 Water Quality Retrofit
Currently, the contractor will be working on the excavation, compaction, installation of water quality structures, construction of curb, gutter sidewalk, and asphalt paving on the HWY 99(68th - 78th St). Right lane, bicycle lane, sidewalk, and bus stop will be closed during construction activities. The travelling public can expect delays due to construction between the NE 68th – NE 78th St. along HWY 99.
The new bridge on Northeast Davis Road is now open to traffic. There is still ongoing work to complete the project and the travelling public can expect delays due to flagging operations at the bridge.
Northeast 10th Avenue (Northeast 149th Street to Northeast 154th Street)
NE 10th Avenue is open to traffic. Plant establishment work, such as weeding, irrigating and replanting, will continue sporadically around the culvert and stormwater facility until February 2025. This may require occasional single-lane closures, but the roadway will remain open to traffic.
Morgan Bridge #0213 (Bridge on NE 182nd Ave at Morgan Creek)
The contractor is working this week at the Morgan Bridge #0213 too. This bridge is a part of the Strengthening Bridge Bundle #2 Project also. Scan and Layout Reinforcement and Coring for Anchor Assembly will be completed by this week. The travelling public can expect delays due to operations at the bridge. If necessary, a road closure and detour will be posted later.
Gibbons Bridge #006 (Bridge on SE Evergreen Hwy at Gibbons Creek)
The contractor will be working on the bridge strengthening activities at the Gibbons Bridge No. 006. The travelling public can expect delays due to operations at the bridge.
Lucia Falls Bridge #116
Lucia Falls Bridge #116 will be closed beginning Monday, Aug. 7. This will close Hantwick Road to through traffic. Northeast 279th Street will also be closed to through traffic east from Northeast 182nd Avenue. The closure is scheduled to last no more than 20 calendar days (through Aug. 26) but may be extended as needed. Exact closure start and end dates are weather dependent and subject to change.
Traffic will be redirected around the bridge via Northeast 172nd Avenue and Northeast Lucia Falls Road. Drivers should follow the directions of signage and flaggers.
Matney Bridge No. 168 (Bridge on NE 68th Street at Matney Creek)
Currently, the contractor is working on the bridge strengthening activities at the Gibbons Bridge No. 006. This bridge is a part of the Strengthening Bridge Bundle #2 Project. Installation and Tension Anchor Assemblies will be completed by this week. The travelling public can expect delays due to operations at the bridge.
Rock Creek Bridge #96
Rock Creek Bridge will be closed beginning Wednesday, Sept. 6, closing Northeast 152nd Avenue to through traffic. Northeast 279th Street will also be closed to through traffic east from Northeast 182nd Avenue. The previously announced closure start date was Aug. 28.
Drivers traveling north will use Northeast Kelly Road to Northeast Gabriel Road. Drivers traveling south will use Northeast 172nd Avenue to Northeast Boutelle Road, then Northeast 147th Avenue to Northeast 249th Street and Northwest 25th Street.
2023 Slurry and Cape Seals
The contractor will begin work this week to complete some surface treatment. Affected residents should have received a doorhanger with the appropriate date of when the work will impact them. For more information on the schedule, please visit clark.wa.gov/public-works/summer-road-preservation.
NE 102nd St., NE 103rd St, and NE 104th St, ( NE 87th Ave to NE 93rd Ave.)
A private contractor will be working to install a new sanitary for CRWWD for the septic elimination program. Drivers should expect traffic revisions within the area. Work is scheduled to be complete by the end of Sept. 2023.
Northeast 139th St. (10th Avenue)
The contractor for a private developer is working on frontage improvements along with installation of utilities within NE 139th St. Drivers should expect traffic revisions within the area. Work is scheduled to be complete by the end of Oct. 2023.
The intersection of Northeast 99th Street and Northeast 107th Avenue has reopened. Sections of Northeast 99th Street and a majority of the newly built road at Northeast 99th Street remains closed. Portions of the newly built road at Northeast 99th Street will be open to local traffic only. The intersection of Northeast 112th Place continues to be closed as the road cannot open until the sidewalks are complete. Construction will continue through fall. Traffic delays of up to 10 minutes are possible in the construction area. Some work, such as landscape planting, may continue into 2024.
NE Amboy Road (NE Morning Dr. to NE McKee Rd)
A private contractor will be working to install a new waterline for Clark PUD. Drivers should expect traffic revisions within the area. Work is scheduled to be complete by the end of Sept. 2023.
City of Vancouver 360.487.7750
Private Development Projects Citywide
A variety of private development projects may be occurring throughout the City of Vancouver. For information about these projects, please visit: www.cityofvancouver.us/projects.