Public Works is moving forward with the redesign construction of the intersection of Northeast 179th Street and Northeast 29th Avenue. The project will replace the existing single lane, all-way stop-controlled intersection with a roundabout-controlled intersection. This change is necessary to accommodate additional traffic volumes associated with residential and commercial development in the area.
Design: spring 2020 – spring 2025
Construction: summer 2025
Click here to see the current project schedule.
State agencies that issue required permits are experiencing backlogs. Acquiring permits is taking longer than expected. This could impact the project timeline. We will provide updates to the project schedule as more information becomes available.
The total budget identified for the project is $23.2 million, including a federal grant for approximately a third of the cost.
Click here to see the current project cost estimate.
Mailers
June 2023 - Postcard (PDF) January 2022- Heads Up (PDF)
August 2021 - Update Heads Up (PDF)
August 2021 Heads Up (PDF)
More information
Scott Sawyer, P.E. project manager
Northeast 179th Street projects
Clark County Public Works
564-397-4364
179thstreetproject@clark.wa.gov